Harvested fields and a finished light-gray warehouse at a quiet suburban edge in late autumn.

Bourbonnais Parkway Exit 318 Development: What's There Now?

In October 2018 the Daily Journal described the land around Interstate 57's new Exit 318 at Bourbonnais Parkway as 1,200 acres "being targeted as a prime area for industrial and business development." Eight years later, the exit has two places to buy fuel. The third project is a construction site behind one of them, and its first building is due in fall 2027.

At Exit 318, development has come at the speed of signed tenants. The newest project is designed around that same rule, so the next few years at the exit will move one lease at a time.

The Exit Was Sold on Acreage

The interchange took a long time to build. Kankakee Valley Construction Co. started the $46.3 million project in late summer 2015, and the ribbon cutting was set for Nov. 2, 2018, according to the Daily Journal's opening report. The paper called the project "perhaps two decades in the making." The work also covered improvements at U.S. Route 45/52, Illinois 50 and County Road 6000N. Exit 318 sits three miles north of Bradley's Exit 315 and four miles south of Manteno's Exit 322.

The pitch has grown since then. The Village of Bourbonnais interchange page now says more than 1,400 acres are available for Industrial TIF, and it advertises Tax Increment Financing, a Business District and two Enterprise Zones as incentives. In a statement on that page, former Mayor Paul Schore said gas, electric, water, wastewater and fiber "are available in abundance," along with access to rail. The Economic Alliance of Kankakee County's site flyer for the Bourbonnais Parkway Business Park also lists the park as TIF-eligible, inside an Enterprise Zone, with utilities on site.

So utilities and incentives were on paper from the start. What came next shows what actually sets the pace.

Two Fuel Stops in Seven Years

The dates below come from the Daily Journal's 2018 opening report, the Village's Gas N Wash and Road Ranger announcements, the Daily Journal's 2021 Road Ranger proposal story, and its September 2026 coverage of PSI's permit and groundbreaking.

Date What happened at Exit 318
Late summer 2015 Interchange construction begins
Nov. 2, 2018 Interchange opens to traffic
May 2019 Gas N Wash breaks ground at the southwest corner of Bourbonnais Parkway and Route 45/52
Feb. 2020 Village marks Gas N Wash as the exit's first business
June 2021 Road Ranger travel center proposed, with opening projected for late 2022 or early 2023
Feb. 12, 2024 Road Ranger holds its grand opening at 5210 Quebec Drive
Aug. 27, 2026 Public hearing on PSI Construction's warehouse permit
Sept. 22, 2026 PSI breaks ground on its first warehouse
Fall 2027 PSI's target for completing the first building

Gas N Wash opened as a 7,000-square-foot building with a convenience store, a Dunkin' Donuts, a Ta Canjio Taco Truck and fuel islands. A separate 4,900-square-foot car wash sat alongside, according to the Village's 2020 announcement.

The Road Ranger story shows how slowly things moved. In June 2021 the Daily Journal reported that the company had bought an 11-acre lot on the southwest side of the interchange, with a $9 million to $10 million investment and 60 to 70 jobs planned. In the same story, Schore said the village had not had serious discussions with any other business about the area. He added that a 10.4-acre lot at the southeast corner of Bourbonnais Parkway and U.S. 45/52 had "drawn a lot of interest."

The travel center opened in February 2024, about a year past even the late end of that projection. The Village's grand opening notice listed 80 truck parking spaces, eight diesel lanes, showers, laundry, gaming and EV charging. Food came from Dickey's Barbecue Pit, Church's Chicken, Subway, Dan's Pizza, Road Ranger Kitchen and Tejas Tacos.

Both businesses had a ready customer the day they opened: the cars and trucks already using the exit. A fuel stop doesn't need to recruit anyone. A warehouse does, and that difference is why the first non-fuel project took until 2026.

PSI Builds First and Looks for Tenants After

In September 2026 the Bourbonnais Village Board granted PSI Construction a special-use permit for a planned unit development at the southeast corner of Route 45 and Bourbonnais Parkway. The land was already zoned for manufacturing. The permit allows four light industrial buildings and an access street. The Daily Journal's groundbreaking report puts the complex at $40 million: four warehouses of about 100,000 square feet each on 48 acres, along Quebec Drive behind the Road Ranger.

The phasing is what matters most. PSI described this sequence to the village:

  1. Build a warehouse of about 111,600 square feet that the company will lease out. The building can be subdivided or expanded.
  2. Recruit tenants once construction is underway.
  3. Start the second building only after the first one leases.
  4. Repeat for the third and fourth buildings.

PSI officials told the Daily Journal that the first building would take about 10 months to build. They expect the full project to take two to three years. At the groundbreaking, co-owner Justin Goselin said the company was already talking with future tenants to shape the first building. He also said he hopes to bring in manufacturing, not only storage.

PSI is based in Kankakee and has built a lot locally. It is construction manager for Bradley-Bourbonnais Community High School's $74.5 million expansion and the $5.7 million first phase of Kankakee's East Riverwalk. It also managed the River Valley Metro Mass Transit bus garage and helped oversee the Bradley 315 Sports Complex.

With that much local work behind it, PSI still chose to tie each new building to a signed lease. The builder is betting on the exit one building at a time.

The "First Domino" Falls When a Lease Is Signed

Mayor Jeff Keast described the project to the Daily Journal as the start of a chain:

"This is the first domino. I'm extremely excited. This is a huge advantage for the community."

In the same report, Keast said investors keep showing interest and that hotels, manufacturing and other businesses have been discussed. "We're really close to having those things cross the finish line," he said.

PSI's own plan shows what makes the dominoes fall. Phase 2 begins when Phase 1 has a tenant. Any hotel or plant the mayor mentioned would need its own signed operator before anything is built. Groundbreakings make the news, but at this exit the signed leases set the schedule.

The incentives listed on the village interchange page are part of that math for developers. They include TIF, Business District reimbursements, and Enterprise Zones that offer a five-year property tax abatement plus sales tax exemptions on building materials and equipment. The Road Ranger deal shows how these tools have been used here. In 2021, representatives of the landowner's developer asked trustees for $1.5 million in TIF for infrastructure work on three connecting lots south of the parkway, including the Road Ranger parcel. The Daily Journal explained that TIF districts let local governments fund infrastructure "through the property taxes generated within the district's boundaries." Trustees approved having attorneys for all parties work out the details. Incentives like these can lower a developer's costs, but the developer still needs a tenant.

What This Means If You're Weighing Bourbonnais

The interchange itself is the part that's finished. Since November 2018, Bourbonnais has had its own I-57 exit between Bradley's and Manteno's, along with the road work on Route 45/52, Illinois 50 and County Road 6000N that came with it. That access is already in place.

The commercial build-out around the exit is a different kind of promise. It has moved slowly. The first business took about 15 months after opening, the travel center arrived about a year past its projection, and the first non-fuel project broke ground nearly eight years after the exit opened. The next stage is tied to leasing by design. A realistic expectation for the next few years is one 111,600-square-foot building finished around fall 2027, with more to follow as each one leases.

Buyers comparing homes near the Route 45 and Bourbonnais Parkway corridor will get the clearest picture from what is built, permitted or under construction. Bourbonnais Village Board approvals, like the September vote on PSI's permit, are the earliest public sign of the next project. A mention of interest in a hotel is not.

Common Questions

What is at Exit 318 right now? The Gas N Wash at the southwest corner of Bourbonnais Parkway and Route 45/52 opened in 2020. The Road Ranger Travel Center at 5210 Quebec Drive held its grand opening in February 2024. PSI Construction's first warehouse has been under construction behind the Road Ranger since the Sept. 22, 2026 groundbreaking.

When will the warehouse complex be finished? PSI's target is fall 2027 for the first building, with two to three years for all four. The second, third and fourth buildings each start after the previous one leases.

Is a hotel coming to the exit? In September 2026, Mayor Keast told the Daily Journal that hotels, manufacturing and other businesses have been discussed. The permit the Village Board approved in September covers PSI's four light industrial buildings.

If you're deciding whether a home near Bourbonnais Parkway is priced for what the exit is today or for what it might become, Leanne Provost can walk you through recent sales nearby and what has actually been approved along the corridor. Schedule a free consultation, or get your instant home valuation to see where your property stands.

Work With Leanne

Trust her for dedicated, expert real-estate service in Bourbonnais and the surrounding region. With her market insight, client-first commitment, and strong negotiation skills, she makes your buying or selling process smooth and successful.

Follow Me on Instagram